plaster
A few delays the past couple weeks as Winter sets in. Our plaster was installed about a month ago but was installed before the roofing was complete, and as a result some rooms were badly water damaged. The Darbecca report revealed a few items (dating back from the slab inspection) still hadn't been rectified, and our confidence in our BC is fading. We were told the plaster in our bedroom had been replaced, but having compared photos it is obvious the have just patched up the holes and will paint over it. Hmm. Awaiting their response (ie get written confirmation it "has been replaced") before we show them the contrary evidence, unless for whatever reason the BSS inspector said it wasn't damaged enough to warrant replacing. I just hope it doesn't swell or begin to droop, I just want to move in already!!